| 08/02/07
| CRC completes the course at hospital |
An increasing demand for pharmacy aseptic services has inspired
the completion of a new £1.7million manufacturing and dispensing
facility at University College Hospital London (UCHL) by specialist
contractor Clean Room Construction Ltd.
 |
|
 |
| Before
and after: (Left) a typical room with Georgian windows
in UCHL’s building and (Right) the refurbished
interior with same window in background |
Close collaboration between the central London hospital’s
pharmacists and Clean Room Construction (CRC) project
team has resulted in a modern facility which is regarded as a key
element of the National Health Service’s strategy to develop
better pharmaceutical manufacturing within hospital pharmacies.
The hospital pharmacy was awarded a government grant to create the
facility in a bid to overcome shortage problems associated with
the commercial supply of drugs.
Diagnosis
Demand for pharmacy aseptic services is growing, partly due to the
support required for the hospital’s important clinical work
in the areas of intensive care, surgery, gastroenterology, cancer,
paediatrics and neonatology. The demand is likely to increase further
with the expected publication of National Patient Safety Agency
guidelines on promoting the safe use of injectable medicines in
the spring.
The brief from UCHL focussed on the need to bring all the pharmacy
manufacturing and quality control facilities on to one site and
to create a modern aseptic dispensing facility.
Prescription
Although the aseptic unit design might have included hydrogen peroxide
gassing (a sanitisation process capable of Log 6 spore reduction),
it was clear early on that the budget would not allow this approach.
Space in the hospital was even more scarce with the old basement
staff canteen identified for the new tablet manufacturing unit (120m_)
and the 4th floor of the building (900 m_) earmarked for the aseptic
and repack units.
Ian Isted, CRC’s projects manager, said:
“The project presented many challenges for our team to overcome.
It was an old hospital in central London and the site was occupied.
As well as working with very restrictive heights and at two levels,
a basement and a fourth floor, we were up against a tight deadline
and budget constraints. Internal pillars, two stairwells and lift
shafts also had to be accommodated in the design for the new facility.”
A former central corridor with rooms on each side has now been turned
into grade C preparation cleanrooms which are served by Grade D
support areas on one side and grade B dispensing cleanrooms on the
other. A central lift shaft and stairwell split the middle part
of the building into two separate areas. The result was a design
for two separate aseptic facilities, each with a dedicated HVAC,
effectively segregating the aseptic dispensing of chemotherapy drugs
from other non-cytotoxic medicines. The support offices and plant
room have been located between the two aseptic facilities.
A second stairwell has separated the aseptic facilities from non-sterile
manufacturing, comprising grade D clean areas for repacking and
over-labelling medicines, and dedicated rooms for the preparation
of medicines for internal use, such as mixtures and suspensions,
and external use, such as creams and ointments.
The tablet manufacturing facility has a grade D process area with
dust control booths in the process room, providing dedicated areas
for weighing, mixing and granulation and compression. The booths,
manufactured by CPS Extract, re-circulate, through safe change filters
and ceiling HEPA (H14) filters, 1,200 air changes per hour. These
changes are designed to control air borne dust, within a safe working
zone, to below 100µg/m_. Since alcohol is used in one of the
granulation stages, detectors have been installed in the booths
to alarm if alcohol vapour exceeds 25 per cent of the lower explosion
limit.
Principal pharmacist Tony Murphy says: “We opted for class
II biological safety cabinets rather than isolators as grade A work
zones for the dispensing of cytotoxic, antibiotic, antifungal and
antiviral injections. Visits to large commercial aseptic dispensing
units which used unidirectional air-flow workstations and good work
practices in well-controlled environments showed us that a classical
design would achieve exceptionally good microbiological control.
In addition to staff training and validation, the key is good workflow
and segregation of processes.
 |
|
 |
|
Left:
Blending and mixing equipment in the Grade D tableting suite.
Right:
A combined stainless steel pass through and trolley hatch
into a Grade D area. |
Segregation of processes
Three stages of garment change lead into the production areas:
1) Cleanroom labcoat for grade D support areas;
2) Sterile two-piece cleanroom garment with clogs for the grade
C preparation areas;
3) Sterile grade B cleanroom coverall (donned over the grade C garment)
and overboots for the grade B cleanrooms.
Store areas connect to grade D assembly rooms via trolley hatches.
The assembly areas hold no more than two to three days stock. Following
assembly checks, components are sprayed with 70 per cent alcohol
and wiped before transferring through hatches into the grade C preparation
area. In the grade C area components are sprayed with 70 per cent
alcohol and wiped before transferring through hatches into the grade
B cleanrooms. Dispensed medicines are transferred through hatches
into the grade C area for inspection and then into a grade D final
check room prior to release.
Vinyl cladding has been used for floors, walls and ceilings in the
grade B and C cleanrooms and change areas. A Facility Monitoring
System (FMS) has been installed to continuously measure room air
particle counts in the grade B cleanrooms, with sample points in
all other areas. The FMS also monitors room pressure differentials
and refrigerator temperatures.
Remedy
Isted concludes: “The completed facility encompasses four
zones of air conditioning, automatic room pressure and particle
monitoring as well as robust services. Power cuts are frequent occurrences
in old buildings and the services are designed to cope with this
sort of disruption to maintain a clean environment.
“A challenging environment like this requires a genuine commitment
to a partnership approach from the outset. The CRC
team worked closely with the pharmacists to ensure that we created
a customer-specific solution. The cooperation and support we received
from principal pharmacist Tony Murphy and his team was crucial to
the design and construction of a first class facility which meets
all the customers’ needs.”
Murphy adds: “The professional approach adopted by Clean
Room Construction for this complex design and build project
has led to the production of an impressive facility here at University
College Hospital London.”
Microbiological testing is now under way and it is hoped that aseptic
preparation can begin in March. Aseptic preparation requires regular
external audit by pharmacy QA specialists. However, the UCLH pharmacy
team plan to manufacture medicines for which a licence is needed.
This ‘specials licence’ is required when medicines are
manufactured as ‘a batch’ for more than one patient,
when the expiry period on the product exceeds seven days (sterile
medicines)/28 days (non-sterile medicines), or when the medicine
is prepared for another hospital. While the majority of injections
are administered within 72 hours of preparation, there are instances
when patients need home therapy requiring the manufacture of injections
in advance of use.
Licensed manufacture is expected to begin in May 2007.
|
CRC
- Units K1/K2
Temple Court
Knight Road
Strood
Rochester
Kent, UK - ME2 2LT
T: +44(0)1634 295111
F: +44(0)1634 294100 |
|