CRC were
responsible on a design and build basis, for the clean rooms
and laboratories in their entirety and for the M&E services
to the rest of the facility. The remit included commissioning,
validation and hook-up attendance upon the client’s
equipment.
|
| Project
Outline: |
|
CRC were initially employed
alongside the Client’s professional team from Stage
C to produce a performance specification for the works which
formed the basis for design and build tenders which we tendered
on a competitive basis.
The works comprised of approx. a total of 1,600m2 of accommodation
including 1,200m2 of clean rooms / laboratory space and 400m2
of offices.
The services included liquid nitrogen, process cooling water,
compressed air, vacuum, low pressure hot water, chilled water,
18 MegOhm de-ionised water, HVAC, fume extraction, fire detection,
data & voice.
The clean rooms included Class 10, 100, and 1,000 classification
areas and were complete with wet benches.
The offices included heat pump air conditioning
|