MANUFACTURERS
| Client: |
|
J.D.S
Uniphase |
| |
|
|
| |
|
“A world wide player specialising in
the design, development, production and distribution of a
range of products in fibre optic communications and state-of-the-art
networks”
|
| Project
Name: |
|
New Manufacturing
Plant |
| |
|
|
| CRC’s
Responsibilities: |
|
CRC were
employed as the main contractor on a full turnkey design and
build basis. Commissioning, validation and hook-up attendance
upon the client’s equipment suppliers was included.
CRC acted as the Principal Contactor and Planning Supervisor.
CRC were responsible for planning, building control and statutory
authority approvals
|
| Project
Outline: |
|
CRC initially provided design
services to produce the Employer’s Requirement Document
which was in a performance specification format suitable for
design and build contractors to bid against. CRC then negotiated
for and were awarded the design and build contract.
The project was for the development and fitting out of five
speculatively built warehouse/office buildings to house clean
room and office facilities.
Additional accommodation space was created by the installation
of new mezzanine floors.
External accommodation was created for liquid nitrogen and
chemical storage, chillers, transformers and standby generators.
The total square area was 5,250m2
The clean rooms included Class 1,000 and 10,000 classification
areas.
Services included upgrading of incoming utilities, liquid
nitrogen, specialist gases, automatic chemical waste handling,
clean room and office HVAC, fume extraction, automatic fire
detection, building management systems.
|
| Contract
Value: |
|
Circ £4.0m |
|
CRC
- Units K1/K2
Temple Court
Knight Road
Strood
Rochester
Kent, UK - ME2 2LT
T: +44(0)1634 295111