To view this image album of our work, you require Flash
CRC's Responsibilities: CRC was employed for its third major project at Protherics UK Ltd, for the full design and build, for construction, mechanical and electrical services, to expand the existing manufacturing area by 575m².
Project Outline:
The facility design was integrated into the existing and new build
extension and interfaced with the existing manufacturing suite.
The facility area totalled 575m² and was designed to a background
cleanliness levels of ISO Class 7 and ISO Class 5 vertical laminar flow
hoods incorporating speed control fan filter units located within
the CRC modular ceiling grid system.
Location: West Wales
Duration: 9 months